July 2024 - The Township Committee awarded the construction contract to Ernest Bock & Sons of Philadelphia for $19,685,000. Also awarded was the HVAC Commissioning contract to Concord Engineering of Cherry Hill. The contract documents will now be drafted before a Notice to Proceed is issued.
June 2024 -- The Bid Opening for the Construction of the New Municipal Complex were received on June 25, 2024. Eight bids were received. The bid price ranged from $19,685,000 to $26,400,000. The bid tabulation is now available. The bid packages are currently undergoing legal and technical review. The Township Committee expect to award the contract at its July 15 meeting. Bids for the HVAC Commissioning and Material Testing services will be received by the Township on July 3, 2024.
May 2024 -- The bid specifications for the construction project is now available. The updated project timeline is as follows:
May 15, 2024 | Construction Bid Package Issued |
May 25, 2024 | Pre-Bid Meeting (attendance is optional) |
June 25, 2024 | Bids Due |
July 15, 2024 | Award of Construction Contract |
September 2024 | Construction Begins |
January 2026 | New Municipal Complex Opens |
January to March 2026 | Demolition of Current Building |
April 2024 -- The Township has received approval to bid the project from the New Jersey Office of State Comptroller.
February 2024 -- The Construction Bid documents were submitted to New Jersey's Office of State Comptroller for review. The layout of the police department is being reviewed by the Department of Corrections. Phase 1 of the environmental site assessment and the ground penetration survey of the site is underway. If approvals are received, intention is to open bidding for the construction in spring 2024 with the project to being in the summer.
October 10, 2023 -- Following the initial cost estimate, an updated design was presented to the Committee. Next steps involve regulatory design reviews and preparation of the construction bid documents.
October 10, 2023 New Municipal Complex Presentation
May 22, 2023 -- Mark Coan, Principal at IEI Architects, presented to the Township Committee an update on the site plan and building design. The next steps will involve estimating the proposed costs and the interior design.
May 22, 2023 New Municipal Complex Presentation
February 27, 2023 -- The following presentation was made at the Township Committee meeting outlining the concept plan for the new municipal complex. The preferred concept plan (Plan Option #2B) is a two-story facility that will connect to the existing Senior Community Center. The Senior Community Center will be upgraded, modernized, and refurbished to match the future newly constructed building. The construction of a two-story building has several benefits, including a more efficient and cost effective construction, a smaller building footprint to allow for greater impervious ground cover (more green space), and provides an opportunity for future expansions and improvements if needed. Strong planning consideration was given to minimize disrupting current operations while the new building is being constructed. The goal is to construct the new facility while maintaining current operations. Once complete, the new complex will be not only the focal point of municipal services, but a public gathering and open space location for all residents of the Township.
February 27, 2023 New Municipal Complex Presentation
Conceptual Site Plan Option #2B
Project Timeline: As of April 2023
Background
The Township of Bordentown proposes to construct a new municipal complex to replace its current facilities located at 1 Municipal Drive in Bordentown Township. Expansion of the existing facility was considered but was determined not to be a cost-effective option. The Township services have long outgrown the current facility, and studies proved the need for an expanded and modernized facility. The new complex will house all municipal departments, including police and municipal court, as well as a senior citizen community center.
The Township previously engaged an architectural firm which designed a single one-story building for an alternate site in the Township. Since the completion of that design, the Township re-evaluated the selected site and has determined that the preferred location is 1 Municipal Drive. Additional parcels to be included in the project include the gravel parking lot behind the current building at 1 Municipal Drive, 3 Municipal Drive (existing Senior Community Center), 803 Farnsworth Avenue (vacant residential home purchased by the Township) and 765 Farnsworth Avenue (vacant restaurant purchased by the Township).
The Township’s goal is to create a “municipal complex” consisting of buildings for municipal operations and parking as well as public amenities. The Township has set aside funding for this project and is prepared to begin the process immediately.
Committee Actions To Date:
Resolution #2024-153 -Awarding the HVAC Commissioning Contract to Concord Engineering (July 15, 2024)
Resolution #2024-152 - Awarding the Building Construction Award to Ernest Bock & Sons (July 15, 2024)
Resolution #2024-144 - Turek Consulting LLC to provide Sitework Inspections (July 15, 2024)
Resolution #2024-91 - Amending the IEI Architect name change to DBZArchNJ, LLC (DesignBlandz) (April 8, 2024)
Resolution #2024-70 - Assigning the IEI Architects contract to DesignBlendz LLC (due to merger) (March 11, 2024)
Resolution #2024-59 - Authorizing Asbestos and Lead-Paint Sampling of Current Building (February 26, 2024)
Resolution #2024-58 - Authorizing Environmental Site Assessment and Ground Penetration Survey (February 26, 2024)
Resolution #2023-199 - Amending Award to IEI Architects (August 21, 2023)
Resolution #2023-192 - Award of Contract to Demolish 795 and 803 Farnsworth Avenue (August 21, 2023)
Resolution #2023-178 - Turek Consulting LLC for Site Design (July 17, 2023)
Resolution #2023-82 - IEI Architects for Architectural Design Services (March 13, 2023)
Resolution #2022-267 – IEI Architects for Concept Design (November 28, 2022)
Resolution #2022-266 - Turek Consulting LLC Environmental Study and Survey (November 28, 2022)
Resolution #2022-252 – Epic Management, Inc. to provide Construction Management Services (October 24, 2022)
Resolution #2022-239 – Authorizing Use of a Project Labor Agreement for the Municipal Complex Construction Project (September 26, 2022)
Ordinance No. 2022-08 – Financing of $17,500,000 for the Planning, Design & Construction (May 23, 2022)
Resolution #2022-110 – Location of New Municipal Complex (April 25, 2022)